The renovation of Asbury Memorial's sanctuary is estimated to be a 6 month long project which began May 4 and will cost 1.5 million dollars. If you would like to contribute to this project, you may do so via our web site...just click on "Support Asbury" or send a check to Asbury Memorial United Methodist Church ...1008 Henry Street, Savannah, GA 31401.

Click picture on left for a larger view of an artist’s rendition of the new sanctuary

Follow the weekly progression of our sanctury renovaton

May 10 ... Click on any picture for a larger view

May 17 ... Click on any picture for a larger view

June 7 ... Click on any picture for a larger view

June 14 ... Click on any picture for a larger view

June 21 ... Click on any picture for a larger view

June 28 ... Click on any picture for a larger view
Prep work being done for the balcony extention ... kneeling area around altar ... electrical conduits added

July 5 ... Click on any picture for a larger view
Main work this week was the placement of the main support beam for the balcony extension ... work also peformed on the bell tower

July 12 ... Click on any picture for a larger view
Main work this week was the erecting of the scaffolding to work on the ceiling ... work also performed on the balcony extension

July 19 ... Click on any picture for a larger view
Main work this week was above scaffolding setting in the Heating Air Conditioning ducts

August 2 ... Click on any picture for a larger view
Main work this week continues above scaffolding setting in the Heating Air Conditioning ducts and light and fire extinguishers along with work on the balcony floor

August 9 ... Click on any picture for a larger view
Main work this week continues above scaffolding setting the light fixtures in ceiling and on the balcony floor

August 16 ... Click on any picture for a larger view
Main activity this week continues above scaffolding setting the light fixtures and ceiling work

August 30 ... Click on any picture for a larger view
Main activity this week continues above scaffolding finishing the light fixtures and ceiling work

September 6 ... Click on any picture for a larger view
Main activity this week was dismantling the scaffolding revealing the completed ceiling work and new air ducts

September 13 ... Click on any picture for a larger view
Main activity this week was work in the balcony and opening the sanctuary floor for Sunday Q & A

September 27 ... Click on any picture for a larger view
Main activity this week was flooring in the balcony ... setting in sound system ... finishing celiling stage lighting

October 11 ... Click on any picture for a larger view
Main activity this week was beginning laying of new floor in sanctuary along with minor work along walls and balcony

October 18 ... Click on any picture for a larger view
A lot of work done this week ... laying of new floor in sanctuary and altar area, walls painted, altar rail reassembled